Completed Projects

Since 1993 Insist Avtomatika completed more than 300 projects of process control systems in oil production and other industries acting as a system integrator or main automation contractor.
  • Oil and gas
    • Oil Company ROSNEFT
      • Design, supply, start-up and commissioning of process automation system of well pads. Development of Gorshkovskaya ploschad of Priobskoe field, Oil and gas production shop - 21 Yuganskneftegas JSC , 2012–2014
      • Design and supply of process automation system of ROSPAN INTERNATIONAL CJSC facilities. First and second stages of East Urengoiskoe and Novo-Urengoiskoe license areas, 2013-2014
      • Design, supply of equipment, start-up of the automated safety control system (PAS and automated fire safety control system). Development of Vankor group of fields, Vankorneft CJSC, 2009-2014, including:
        - main pipeline
        - preliminary water discharge unit Yug, oil pumping station, well pad pump station, operations base, etc.
        - automated fire safety control system of the crude oil treatment facility
      • Design, supply of equipment and commissioning of process automation system of well pads of the central processing facility Aktiv Kamennoe, RN-Nyaganneftegaz JSC, 2012-2013
      • Design and supply of equipment of process automation system and automated fire safety control system of RVS-10000 at oil pumping station of Prirazlomnoe oil field, Yuganskneftegas JSC, 2012-2013
      • Design, supply of equipment of oil treatment automation system of crude oil facility-6. Retrofitting. Yuganskneftegas JSC, 2012-2013
      • Feasibility study, design, supply of equipment and information systems, start-up of process automation system and IT solutions of process facilities of the Uvat group of fields, TNK-Uvat, 2007-2013:
        - Design of the process automation system for well pads of Urnenskoe field
        - Process automation system of the central oil gathering facility of Ust-Tegusskoe field
        - Development of process information management system of Ust-Tegusskoe and Kalchinskoe fields
        - Design of process automation system and automated fire safety control system of gas-turbine power station of Tyamkinskoe field
      • Design of process automation systems for power supply facilities of Priobskoe field, 2008-2009
      • Design, supply of equipment and start-up of process automation system and fire safety control system for oil and gas production and treatment facilities of Yuganskneftegas JSC, 1998-2012:
        - Crude oil facility-5 of Pravdinskoe oil field
        - Oil pumping station Prirazlomnoe
        - Central oil gathering plant Prirazlomnoe
        - Fire safety control system of booster pumping station-5 with preliminary water discharge facility of Malobalykskoe oil field
        - Oil treatment and transportation monitoring system of Priobskoe, Prirazlomnoe and Pravdinskoe fields
        - Reservoir pressure maintenance facilities of Priobskoe field
        - Central oil gathering plant-2 of Priobskoe field
        - Oil and gas pipelines of Priobskoe, Prirazlomnoe and Pravdinskoe fields
        - Central oil gathering plant-1 of Priobskoe field
        - Field facilities of Priobskoe field
        - Central oil gathering plant Pravdinskiy

      • Design, supply, start-up of process automation systems for oil heating furnaces and line heaters for the following fields and facilities:
        - Severo-Varyeganskoe field, Varyeganneftegas JSC, 2013 – till present
        - Central processing facility Rostashinskaya, Orenburgneft, 2013
        - Central processing facility of crude oil treatment facility-1 Pokrovskie GS, Oil and Gas Production Department Buzulukneft, Orenburgneft JSC, 2011 – till present
        - Central processing facility Bobrovskaya, Orenburgneft JSC, 2012 – till present
        - Booster pumping station of Novo-Molodezhnoe field, RN-Nizhnevartovsk JSC, 2009
        - Central processing facility-1 of crude oil treatment facility-1 of Khokhryakovskoe field, Varyeganneftegas JSC, 2009-2010
    • Oil Company GAZPROM NEFT
      • Gazpromneft-NNG facilities (including facilities of subsidiary Gazpromneft-Muravlenko):
        - Booster pump station-2 of Ety-Purovskoe field
        - Booster pump station-1 of Vyngapurovskoe field
        - Booster pump station-4 of Muravlenkovskoe field
        - Central oil gathering plant of Vyngayakhinskoe field
      • Design of process automation system for the oil stabilization facility of the Nadym-Pur-Tazovsk region, Gazprom, 2013
      • Design of process automation system for the period of pilot development of Kovytkinskoe gas condensate field, Gazprom, 2013
      • Design, supply and start-up of process automation system for power conduit between central oil gathering plant of Vyngapurovskoe field and preliminary water discharge unit of Pogranichnoe field, 2012-2013
      • Design of process automation system of gas compression station for the facilities of Gazpromneft-Noyabrskneftegaz, 2012
      • Design, supply and start-up of process automation system for central processing facilities, Gazpromneft-Khantos (2006-2009):
        - Booster pump station of the South part of the Priobskoe field
        - Booster pump station of the Kholmistoe field
        - Booster pump station of the Chatyl’kinskoe field
      • Design, supply and start-up of automation systems of oil heaters and line oil heaters for the following facilities:
        - Preliminary water discharge unit of the Orekhovskoe field, 2013
        - Preliminary water discharge unit of the Pal’yanovskoe field, 2013
        - Zimnee field, Gazpromneft-Khantos, 2012
        - Condensate pipeline of 1A area of Achimovsky deposit at the Urengoiskoe field, second (redundant) line, 2012
        - Central processing facility of Kazanskoe oil-gas condensate field, Tomskgazprom, 2012
        - Gas condensate processing facility of Urengoiskoe field, Achimgaz, 2012
        - Central processing facility at Priobsky south licensed area, 2012-2013
        - Central processing facility at Priobsky oil production territorial subdivision, 2010-2011
        - Separation joints of Archinskoe and Nizhneluginetskoe fields, Gazpromneft-Vostok
    • SALYM PETROLEUM DEVELOPMENT N.V.
      • System integration of the Salym group of fields, 2004 – till present
      • Design, supply of equipment and start-up of process automation system, automated fire-fighting control systems for the facilities of the Salym group of fields (2004 – till present):
        - Gathering and transportation of oil, Custody Transfer Facility and Leak Detection System
        - Central processing facility of Salym group of fields
        - Formation pressure maintenance systems
        - Power supply systems including power generation plant
        - Treatment facilities
      • Maintenance and modification of software and hardware of process automation system of the Salym group of fields, 2006 – till present
    • Oil Company LUKOIL
      • Design, supply of equipment, start-up of process automation system for Kogalym oil refinery (1st stage), LUKOIL-Western Siberia, 2011-2014
      • Design and equipment supply of process automation system for isomerization unit of Kogalym oil refinery, LUKOIL-Western Siberia, 2014
      • Design, supply of equipment and start-up of process automation system and automated fire safety control system for oil treatment facilities, LUKOIL-Western Siberia (2000-2014):
        - Compressor station at the Severo-Danilovskoe field
        - Multiphase pump station at booster pump station-12, Danilovskoe field
        - Vacuum-compressor station at booster pump station-2, Kechimovskoe field
        - Booster pump station-2, Severo-Pokachevskoe field
        - Booster compressor station, Lokosovskoe gas treatment plant
        - Custody transfer facilities (including LACT) as part of fiscal metering skid reconstruction program
        - Product pipeline Motor fuel plant – Fuel and lubricants base – Airport
        - Central oil gathering plant of Pokachevneftegaz
        - Central processing facility of Pokachevneftegaz
        - Central oil gathering plant of Urayneftegaz
      • System integration, design, supply of equipment and start-up of process automation system for production facilities and information and control system of Nakhodka gas field (2004-2005):
        - Gas well pads and gas gathering lines
        - Gas pipeline between Nakhodka field and gas compressor station Yamburgskaya
        - Power supply package
        - Auxiliary facilities
        - Upper level of information and control system of Nakhodka field
      • Design of process automation system of production facilities and information and control system of Pyakyakhinskoe gas field, 2013 – till present:
        - Gas well pads and gas gathering lines
        - Gas trunk pipeline
        - Central processing facilities
        - Formation pressure maintenance facilities
        - Associated gas compressor station
      • Design, supply and start-up of automation systems of oil heaters and line heaters for the following facilities:
        - Yuzhnoe Khylchuu field, LUKOIL-Severneftegaz, LUKOIL-Komi, 2012-2013
        - Tevlino-Russkinskoe field, LUKOIL-Western Siberia, 2012 – till present
    • Oil Company RUSSNEFT
      • Design, equipment supply and start-up of process automation system for oil production and formation pressure maintenance facilities of Belkamneft JSC, 2005-2013:
        - Chernovskoe
        - Smolnikovskoe
        - Zabegalovskoe
        - Buranovskoe
        - Pogranichnoe
        - Debesskoe and other fields
      • Design, equipment supply and start-up of process automation system for oil treatment facilities of Belkamneft JSC, 2006-2010:
        - Central processing facility Vyatka
        - Central processing facility Ashit
        - Central processing facility Zabegalovo
        - Central processing facility Buranovskaya
    • TATNEFT
      • Design, equipment supply and start-up of process automation system of complex crude oil treatment plant-2 of Elkhovneft oil and gas production department, 2008-2012
      • Design, equipment supply and start-up of process automation system for complex crude oil treatment plant-1 of Kichuy Elkhovneft oil and gas production department, 2004-2006, 2013
      • Design of process control systems of product heating facilities of heavy coker gasoil hydroprocessing unit of petrochemical plants in Nizhnekamsk, 2014 – till present
    • BASHNEFT
      • Design, supply and start-up of automation systems of oil heaters and line heaters for the following facilities (2012-2013):
        - Bashneft-Dobycha
        - Oil gathering facilities Mancharovo, Telepanovo, Kazankulovo
        - Oil pumping station Keremetovo
  • OIL REFINING
    • Oil Company ROSNEFT
      • Design and start-up of process control system for turbounit of EP-300 facility, Angarsk polymer works, 2012-2013
      • Design and start-up of process control system of liquefied petroleum gas storage tank, Angarsk polymer works, 2014
      • Design of process control system for benzol production unit, Angarsk polymer works, 2014
      • Design of process control system for off-site process facility (technical re-equipment). Novokuybyshev oil refinery, 2013-2014
      • Design and start-up of process control system for catalytic reforming unit and process control system for isomerization unit. Novokuybyshev oil refinery, 2013-2014
      • Design, supply and start-up of process control system for chemical water treatment, Tuapse oil refinery, 2012-2013
      • Design of process control system as part of technical re-equipment of furnace equipment for stabilization unit, facility Л-24-6, Saratov oil refinery, 2012–2013
    • Oil Company GAZPROM NEFT
      • Design and start-up of oil heaters for cracker, Moscow oil refinery, 2012-2013
      • Start-up of instrumentation and process control system for dead oil loading rack and tank farm, Omsk oil refinery, 2012-2013
      • Design and start-up of process control system for isomerization unit, Moscow oil refinery, 2012-2013
      • Process control system of viscosity breaking facility. Design of operator room, Moscow oil refinery, 2012-2013
      • Design and start-up of process control system for hydrogen generation unit, Omsk oil refinery, 2011-2013
      • Development of fiscal metering unit, start-up, Omsk oil refinery, 2010-2011
      • Construction and assembling operations, startup and commissioning of loading and discharge terminal for stable gas condensate, Omsk oil refinery, 2014
    • ORSKNEFTEORGSINTEZ
      Design, supply and start-up of process control system for oil heaters П-1, П-11, Orsky oil refinery, 2011-2012.
  • Metals and Mining
    • NORILSK NICKEL
      • Implementation (jointly with MINCOM Ltd.) of control system of production assets Mincom Ellipse at enterprises of Norilsk Nickel, 2005
      • Project of integration of Ellipse (Mincom) and process control system of ore-dressing and processing enterprise and metallurgical treatment, Norilsk Nickel, 2005
      • Design of process control system of supervisory control of Mayak and Komsomolskiy mines, Talnakhskoe mining department, aboveground part, 2005-2006
      • Design of process control system for melting compartment of metallurgical shop of copper plant, 2004-2006
      • Design, supply of equipment for process control system of supervisory control of Skalisty mine, aboveground part, 2003-2007
      • Design of process control system for sintering plant agglomachines 5-7, 2003
      • Design of process control system for the central air intake building of sintering plant, 2003-2004
      • Pilot project of Invensys Avantis.PRO EAM system (Invensys) implementation. The system is designed for maintenance and repair works control at sintering plant, 2003
      • Design, supply of equipment and start-up of process control system for natrium bisulphite production at sintering plant, 2002
      • Design, supply and implementation of railway transport traffic automated control system. The system is designed for identification, rolling stock accounting system and traffic supervision system. Norilsk industrial area, 2002
    • VYKSA STEEL WORKS
      Complex of works for replacement of control system built on controllers Melplac-550 (Mitsubishi) with a control system based on SIEMENS software and hardware. The system is designed for a section of tube-rolling mill of electric tube-welding complex producing medium-diameter tubes in electric welding shop No. 5, 2006-2008
  • Tire Industry
    • OMSKSHINA (SIBUR)
      Design, supply of equipment and start-up of process control system for mixing and dosing line of rubber compound production section, 2005-2006
  • Heat and power generation, infrastructure
    • INDUSTRIAL HEAT AND POWER ENGINEERING
      • Process control station for boiler room (2 boilers DE-25, 3 boilers DE-16). Omsk plant of building structures. Design, supply, startup. 1995-1997
      • Information-measuring system for boiler room (3 boilers DE-10). Dairy and canning plant, Omsk. Design, supply, startup. 1996
      • Process control station for boiler room (3 boilers DKVR-10) Poultry factory Irtyshskaya, Omsk. Design, supply, startup. 1998
      • Process control station for boiler room (3 boilers PTVM-50, 2 boilers DE-16) Sibkriotekhnika JSC, Omsk. Design, supply, startup. 1998-2002
      • Process control station for boiler room (2 boilers DE-16) CITROBEL CJSC (citric acid plant), Belgorod. Design, supply, startup. 1999-2001
      • Process control station for boiler room of Omsk oil refinery (2 boiler-utilizer with fuel treatment) Sibneft JSC. Design, supply, startup. 2000
      • Process control station for boiler room (2 boilers DE-16, 1 boiler DKVR-10, 2 boilers KVGM-20) Omskgidroprivod JSC, Omsk. Design, supply, startup. 2000-2001
      • Process control station for boiler room in KS-14 (3 boilers DEV-16, boiler room equipment, gas treatment) TNK-Nizhnevartovsk JSC. Design, supply, startup. 2002
      • Process control station for boiler room (1 boiler KVGM-4, 2 boilers PKGM-6,5, boiler room equipment) Strezhevoy oil refinery, Strezhevoy. Design, supply, startup. 2002-2003
      • Process control station for boiler room Kichuy (2 boilers DE-16-14, boiler room equipment) Elkhovneft oil and gas production department, Tatneft JSC, Almetievsk. Design, supply, startup. 2003
      • Heating control station for boilers KVGM-50 of boiler room (2 boilers KVGM-50, 3 boilers PTVM-30) Omskiy bekon JSC. Design, supply, startup. 2004-2005
      • Control system of power supply package at Nakhodka gas field. Boilers UNIMAT UT-3050 produced by LOOS-INTERNATIONAL; FMS machine TBG620V16K produced by Deutz AG; gas-distributing unit, power indoor switchgear 6 kV, SG-0,4 kV, Utilities Transformer Substation-2x630 kVA, Explosion-Proof Package Transformer Substation-1x630 kVA, facilities’ switchboard rooms, distribution boards. LUKOIL. Design, supply, startup. 2005
      • Process control system for boiler room of Block Central Heat Distribution Station at Samotlorskoe field (boilers KSV-2) NizhnevartovskNIPIneft JSC, Nizhnevartovsk. Design, supply, startup. 2007
      • Process control system of boiler-utilizer KGT-20 PGP12RM (boiler-utilizer KGT-20), Omsk-polymer. Design, supply, startup. 2008
      • Process control system of boiler room of Booster Pump Station-32 at Samotlorskoe field (boilers KSV-3) NizhnevartovskNIPIneft JSC, Nizhnevartovsk. Design, startup. 2009
      • Process control system of boiler room of Booster Pump Station at Severo-Pokachevskoe and Kechimovskoe fields. Industrial Group Generation. Design, supply, startup. 2008
    • MUNICIPAL POWER ENGINEERING
      • Process control system for I and II stages of boiler room (8 boilers DE-25-14, boiler room equipment, 2 gas-distributing units) Municipal Unitary Enterprise, Pokachi. Design, supply, startup. 2003-2004
      • Process control system for boiler room №2 (3 boilers PTVM-50) Energocomplex JSC, Omsk. Design, supply, startup. 2004
    • HEATING SYSTEMS
      Process control system for booster pump station of Omskenergo heating systems. Design, supply, startup. 2004
    • Power Generation Plants
      • Automation system of power generation plant 45 MW with three Solar turbines
      • Automatic fire suppression system for Gas Processing Facility of Novo-Pokurskaya PGP (Solar turbine) SLAVNEFT JSC. Design, supply, startup. 2001
      • Automatic fire suppression system for Gas Processing Facility of Pokomasovskaya PGP (Solar turbine) SLAVNEFT JSC. Design, supply, startup. 2001
      • Automation system of power generation plant 45 MW, Salym Petroleum Development N.V. Design, supply, startup and commissioning. 2006-2007
      • PGP 20 MW at Ust-Tegusskoe field. System integration, process control system for supporting facilities. Design. TNK-Uvat LLC, 2009
      • Reconstruction of PGP at West Salym field. System integration, process control system for supporting facilities. Salym Petroleum Development N.V. Design. 2010